Hanoi Electricity Corporation mobilizes nearly 200 personnel to support the construction of the Circuit-3 500kV power transmission line project. The project aims to enhance Vietnam's energy security and sustainability, with a deadline of June 30 for completion.

author-image
Nimrah Khatoon
New Update
EVNHANOI Deploys Nearly 200 Personnel for Crucial 500kV Transmission Line Project

EVNHANOI Deploys Nearly 200 Personnel for Crucial 500kV Transmission Line Project

The Hanoi Electricity Corporation (EVNHANOI) has mobilized nearly 200 personnel to support the construction of the Circuit-3 500kV power transmission line project, a key national initiative aimed at enhancing energy security in Vietnam.

This project is vital for Vietnam's energy security and sustainability, as it aims to enhance the national power grid's capacity and reduce greenhouse gas emissions. The successful completion of this project will have a significant impact on the country's economic development and environmental sustainability.

Spanning from Quang Trach in Quang Binh to Pho Noi in Hung Yen, this 519-kilometer project crosses nine provinces in central and northern Vietnam. It is a critical component of the National Power Development Master Plan for 2021-2030, with a vision extending to 2050, which targets net-zero greenhouse gas emissions by mid-century.

Prime Minister Pham Minh Chinh has emphasized the importance of this project for national energy security, particularly for meeting peak electricity demands in the northern region by 2024 and beyond. On June 1, the Prime Minister called for the mobilization of local resources to ensure the project's timely completion. He urged provincial leaders to provide maximum support and create favorable conditions for investors, contractors, and construction units.

To meet the ambitious target of completing the project by June 30, the Vietnam Electricity (EVN) group and the National Power Transmission Corporation (EVNNPT) have deployed nearly 10,000 personnel working around the clock across the nine provinces. The Prime Minister has also called upon local youth union chapters to collaborate with construction units, leveraging the energy and manpower of local young people.

The total investment for the Circuit-3 500kV power transmission line project is estimated at VND23 trillion ($903 million). This significant financial commitment highlights the project's importance in bolstering Vietnam's electricity transmission capacity and ensuring a stable power supply for the northern region during peak periods.

The project aligns with Vietnam's broader goals of reducing greenhouse gas emissions and transitioning to green energy. By enhancing the national power grid's capacity, the transmission line will play a vital role in supporting the country's economic development and energy sustainability.

June 30 deadline approaches, the concerted efforts of EVNHANOI, EVN, EVNNPT, and local authorities will be vital in ensuring the project's timely and successful completion. This collaborative approach highlights the importance of national and local cooperation in achieving Vietnam's energy security and sustainability objectives.

Key Takeaways

  • EVNHANOI mobilizes 200 personnel to support Circuit-3 500kV power transmission line project.
  • Project aims to enhance Vietnam's energy security and reduce greenhouse gas emissions.
  • 519-kilometer project spans 9 provinces in central and northern Vietnam.
  • Total investment estimated at VND23 trillion ($903 million).
  • Project targets completion by June 30, 2024, to meet peak electricity demands in northern region.